East Coast Railway Commissions New FOB At Cuttack Station


11 January 2019

OMMCOM NEWS


Bhubaneswar: A new six-metre wide foot-over-bridge (FOB) was commissioned across all platforms in Cuttack railway station on Friday.

The project, a part of Cuttack Station Development Plan, was completed within a period of 140 days.

The FOB project was sanctioned under 'Umbrella Works' in 2018-19. It is the third six-metre FOB after Bhubaneswar and Bhadrak, commissioned in the Current Financial Year by the Khurda Road Division.

Another FOB which is being planned at Jajpur-Keonjhar Road station will be commissioned in March, 2019.